Townships
Project : Construction of Seawoods Estate Phase-II (Part – I and Part - II) at Nerul, Navi Mumbai, comprising of residential apartments including state-of-the-art finish and facilities, landscaping etc.
Client : City & Industrial Development Corporation Limited (CIDCO).
- Buildings : Stilt + 18 Floors
- Height of Each Building : 63 meters
- Flats : 440 + 252 Nos.
- Total Built up Area : 6.76 Lac + 3.87 Lac Sq. ft
Infrastructural Facilities:
Sub Station, Internal & External Electrification, Fire Fighting, Lifts, Telecommunication, Internal Roads, Parking Bays, UG Tank, Storm Water Lines, Sewer line, external water supply, Landscaping & horticulture including sandpit, children play area, Jogging track etc..
Project : Development of the Games Village at Kancha Gachibowli for National Games 2002 {A fully integrated township on Build, Own and Sell basis near Cyberabad, in Hyderabad, spread over 50 acres, highly eco-friendly}
Client : Andhra Pradesh Industrial Infrastructure Corporation Limited.
- Buildings : Ground + 10 Floors
LGround + 8 Floors
Ground + 4 Floors - Flats : 789 Nos. (17.00 Acres)
- Independent Bungalows : 125 Nos.
- Total Built up Area : 20, 00,000 Sq. ft.
Infrastructural Facilities:
Internal Roads, well-planned Storm water drains, Water Supply & Sanitary works, Electrical works, Street lighting, all underground cabling, Water Treatment Plant & Sewerage Treatment Plant etc.
Project : Lumpsum fixed price no variation contract for the Construction and Commissioning of all the work with 2 years defect liability and one year maintenance period, which will run concurrently from the last date of completion of project for the proposed Housing Scheme at Suryanagar, Igglur, Banahalli, Banglore
Client : Engineering Projects (India) Limited.
- MIG High Rise : 04 Nos. (Ground + 6 Floors)
- LIG Type 2 : 14 Nos. (Ground + 3 Floors)
- HIG A & B : 20 Nos. (Ground + 1 Floors)
- HIG C : 10 Nos. (Ground Floors)
- MIG A : 70 Nos. (Ground Floors)
- MIG B : 62 Nos. (Ground Floors)
- MIG C : 58 Nos. (Ground Floors)
- MIG D : 58 Nos. (Ground Floors)
- LIG A : 95 Nos. (Ground Floors)
- LIG B : 104 Nos. (Ground Floors)
- Total Built-up Area : 9.53 Lac Sq. ft.
- Type of Structure : RCC Framed Structure
- Foundation : Isolated footings
Project : Mass Housing - Construction of 5552 EWS Houses (Composite work) with Cost Effective Technologies at Baprola, Delhi.
Client : Delhi State Industrial & Infrastructure Development Corporation Limited.
- Houses : 5552 Nos.
- Total Built up Area : 18.45 Lac Sq. ft.
- Multi-Storied Building with Prefab Technology
Project : Construction of 1456 tenements in P+7 Building at Milind Nagar and construction of 2320 tenements in G+4 Building at Sector 22 E under CSRP – BSUP – JNNURM, PCMC area.
Client : Pimpri Chinhwad Municipal Corporation.
- Type of Structure : P+7 & G+4 with Monolithic RCC Load Bearing
Walls with Aluminum Formwork Technology - Total Built up Area : 1.40 Lac Sq. ft.
Project : Construction of Residential Buildings at Upohar, Bengal Ambuja Housing, Chawkgaria, Kolkata.
Client : Bengal Ambuja Housing Development Limited.
- Buildings : Basement + Ground + 19 Storied
- Total Built up Area : 16 Lac Sq.ft.
Infrastructural Facilities:
Drainage Line between Blocks using 900mm dia Hume pipes.
Project : Construction of Residential Housing at Green Enclave, Kadma, Jamshedpur.
Client : Jamshedpur Utilities and Services Company Limited.
- Buildings : Ground + 3 Storied
- Flats : 252 Nos.
- Total Built up Area : 2.77 Lac Sq. ft
Project : Construction of Type I, II, III, IVA, IVB, VA, VB Quarters, RPF Barrack, Training Centre, Administrative Building, GM’s Bungalow, other service buildings Transit Accommodation I & II, Rest House, Officer’s Club House along with allied infrastructure for new Zonal Headquarters for South East Central Railway, Bilaspur (Package – I & II).
Client : South Eastern Central Railway.
- Total Built up Area : 10.63 Lac + 9.96 Lac Sq. ft.
- Buildings : 235 + 266 Nos. Office
- Buildings Basement + Ground + 5 Floors
- Type of Structure : RCC framed Structure with Seismic Design.
Infrastructural Facilities:
Site Clearance, Super Structures on under reamed pile foundation, Staff Quarters, Landscaping & Golf Course, Arboriculture, Internal Road, External Electrification, External Water Supply, External Gravity Sewers, Collecting Well Pump House, Sewage Treatment Plant and allied work. Electrification & Telecommunication, Lifts, drains, Kerby wall path, Children play area, Jogging track, Air Handling Unit, etc.
Project : Construction of Housing Project for Defence Personnel at Ambala (Haryana) - RCC Framed Structure (Package - I, II & III)
Client : National Building Construction Corporation Limited.
- Total Built up Area : 7.85 Lac Sq. ft.
- Buildings : 1004 Nos. (Ground + 2 Floors)
Infrastructural Facilities:
Internal Electrical, Public Health, Sanitary & External Services and allied works
Project : Indian Oil Corporation Limited Refinery Township, Paradip.
Client : Indian Oil Corporation Limited.
Our landmark residential project in Orissa, IOCL Township was completed in four phases. It includes 600 residential units of different types of quarters (G+1 and G+2), Bungalows (Duplex), Hospital, Guest House, Estate Office, Hostels, Officers Club including swimming pool, shopping centre, high school, welfare centre, sports complex including football ground & tennis court. All residential units have interior facilities like modular kitchen with all accessories, cupboards, showcase, dressing units etc. The total built up area in all phases is 9,72,000 sft.