The passion with which we took up water-related projects and pursued our dreams of reaching water to a vast population… has extended to the Power Sector.

To better lives has been our raison d’etre, and this zeal drove us to the Power Sector. We see that even after so many years, in millions of homes across our country, life comes to a standstill at dusk because there is no electricity.

Committed to bring about a change in this scenario, IVRCL gladly seizes opportunities presented by Governments across the country, in the quest to brighten the rural and urban lives alike.

 
Transmission Lines

765 kV S/C (Quad) Transmission Line from Seoni to Nandanwadi in Madhya Pradesh

Client: Power Grid Corporation of India Limited (PGCIL)

Brief Scope of work: Supply of Equipment & materials and inland transportation & insurance, delivery of equipment / materials, survey, foundation, erection, stringing. testing and commissioning of Tower Package (Package - A1) for 765 KV (2nd Circut) S/C Seoni - Nandanwadi Transmission Line, Part of 765 KV Seoni - Wardha Transmission Line associated with Western Region System Strengthening Scheme - II (set A).

  • Line Length = 126 Kms.
  • Number of Total Towers = 342
  • Number of Total Tower Foundations = 342
  • Number of Total Towers Erected = 342

400 kV D/C Transmission Line from Yeddumailaram to Gajwel in Andhra Pradesh

Client: Andhra Pradesh Power Transmission Corporation Limited (APTRANSCO)

Brief Scope: Supply, Erection, Testing and Commissioning of 400 KV DC line from Yeddumailarm (Shankarapally) to Gajwel (400/220/132 KV) Sub-station on Turnkey Basis

Features:

  • Line Length = 105 Kms.
  • Number of Total Towers = 295
  • Number of Total Tower Foundations = 295
  • Number of Total Towers Erected = 295

400 kV D/C (Quad) Transmission Line from Gurgaon to Manesar in Haryana

Client: Power Grid Corporation of India Limited (PGCIL)

Brief Scope: Supply & Services Contract for Tower Package - A1 for i) 400 KV D/C Quad Line from Gurgaon (PG Sec 71) - Manesar ii) Delinking of Agra - Samaypur and Samaypur - Gurgaon 400 KV Line from Samaypur and making a direct link from Agra to Gurgaon associated with Northern Region Strengthening Scheme (NRSS) - XIII, iii) 400 KV D/C Maneswar - Neemrana- Bhiwadi Transmission Line associated with NRSS-XV and iv) LILO of 400 KV S/C Bhiwadi - Bassi at Kotputli associated with NRSS - XV

Features:

  • Line Length = 17.13 Kms.
  • Number of Total Towers = 54
  • Number of Total Tower Foundations = 54
  • Number of Total Towers Erected = 54

400 kV D/C Transmission Line from Manesar to Neemrana in Haryana

Client: Power Grid Corporation of India Limited (PGCIL)

Features:

  • Line Length = 67 Kms.
  • Number of Total Towers = 197
  • Number of Total Tower Foundations = 197
  • Number of Total Towers Erected = 197

400 kV D/C Transmission Line from Bhiwadi to Neemrana Rajasthan

Client: Power Grid Corporation of India Limited (PGCIL)

Features:

  • Line Length = 48.42 Kms.
  • Number of Total Towers = 137
  • Number of Total Tower Foundations = 137
  • Number of Total Towers Erected = 137

400 kV D/C Transmission Line from Madurai to Trichy in Tamil Nadu

Client: Power Grid Corporation of India Limited (PGCIL)

Brief Scope: Supply of equipments and materials and inland transportation & insurance, delivery of Equipment / materials, survey, foundation, erection, stringing, testing and commissioning of Tower Package - A for LILO of One Circuit of Madurai - Trichy 400 KV D/C Line at Karaikudi associated with System Strengthening - VII in Southern Region under Vendor Development Programme.

Features:

  • Line Length = 48.64 Kms.
  • Number of Total Towers = 139
  • Number of Total Tower Foundations = 139
  • Number of Total Towers Erected = 139

400 kV S/C & D/C Transmission Lines from Chandrapur to Parli in Maharashtra

Client: Maharashtra State Electricity Transmission Corporation Limited (MSETCL)

Features:

  • Line Length = 22 Kms.
  • Number of Total Towers = 39
  • Number of Total Tower Foundations = 39
  • Number of Total Towers Erected = 39

400 kV D/C Transmission Line from Vishnuprayag to Muzaffarnagar in Uttarakhand

Client: Tata Projects Limited

Features:

  • Line Length = 86 Kms.
  • Number of Total Towers = 194
  • Number of Total Tower Foundations = 194
  • Number of Total Towers Erected = 194

400 kV D/C Transmission Line from Palandur to Chandrapur in Maharashtra

Client: Tata Power Company Limited

Features:

  • Line Length = 61 Kms.
  • Number of Total Towers = 219
  • Number of Total Tower Foundations = 219
  • Number of Total Towers Erected = 219

400 kV D/C Transmission Line from Vizag to Kattipudi in Andhra Pradesh

Client: Andhra Pradesh Power Transmission Corporation Limited (APTRANSCO)

Features:

  • Line Length = 92.25 Kms.
  • Number of Total Towers = 251
  • Number of Total Tower Foundations = 251
  • Number of Total Towers Erected = 251

220 kV D/C Transmission Lines from Vapi to Magarwada & Vapi to Kharadpada in Gujarat

Client: Power Grid Corporation of India Limited (PGCIL)

Brief Scope: Supply of Equipment & Materials and inland transportation & insurance, delivery of equipment / materials, survey foundation, erection, stringing, testing and commissioning of Tower Package (Package-A) for 220 KV D/C Vapi - Magarwada & 220 KV D/C Vapi - Kharapada Transmission Line associated with Western Region Strengthening Scheme - II Transmission System.

Features:

  • Line Length = 34 Kms.
  • Number of Total Towers = 106
  • Number of Total Tower Foundations = 106
  • Number of Total Towers Erected = 106

220 kV D/C Transmission Lines from Unchahar to Raibareilly Uttara Pradesh

Client: Power Grid Corporation of India Limited (PGCIL)

Brief Scope: Supply of all equipments and materials and inland transportation, insurance, delivery of equipment / materials, survey, foundation, erection, stringing, testing and commissioning of Turnkey Package for Transmission Lines associated with Unchahar III Transmission System.

Features:

  • Line Length = 45 Kms.
  • Number of Total Towers = 135
  • Number of Total Tower Foundations = 135
  • Number of Total Towers Erected = 135

132 kV D/C Transmission Line from Sewa to Hiranagar in Jammu & Kashmir

Client: Power Grid Corporation of India Limited (PGCIL)

Brief Scope: Supply of all equipments and materials and inland transportation, insurance, delivery of equipment / materials, survey, foundation, erection, stringing, testing and commissioning of Tower Package for 132 KV D/C Sewa-II - Hiranagar Transmission Lines (Package-A) associated with SEWA II Transmission System.

Features:

  • Line Length = 77.5 Kms.
  • Number of Total Towers = 305
  • Number of Total Tower Foundations = 305
  • Number of Total Towers Erected = 305

132 kV S/C & D/C Transmission Lines (Package A-2) in Bihar

Client: Power Grid Corporation of India Limited (PGCIL)

Features:

  • Line Length = 60 Kms.
  • Number of Total Towers = 195
  • Number of Total Tower Foundations = 195
  • Number of Total Towers Erected = 195

132 kV S/C & D/C Transmission Lines (Package -1) in Uttar Pradesh

Client: Uttar Pradesh Power Transmission Corporation Limited (UPPTCL)

Features:

  • Line Length = 250 Kms.
  • Number of Total Towers = 815
  • Number of Total Tower Foundations = 815
  • Number of Total Towers Erected = 815

132 kV S/C & D/C Transmission Lines (Package -2) in Uttar Pradesh

Client: Uttar Pradesh Power Transmission Corporation Limited (UPPTCL)

Features:

  • Line Length = 46 Kms.
  • Number of Total Towers = 135
  • Number of Total Tower Foundations = 135
  • Number of Total Towers Erected = 135